Why Division 03 estimates drift on bid day
Most concrete bust-ups are not arithmetic mistakes — they happen when footings, thickened slab edges, pier caps, and anchor-bolt embeds live on four separate structural sheets and one detail gets skipped.
Pre-pour quantity check (never lump CY across details)
- Spread & continuous footings: Separate width x depth x LF per footing schedule mark (
F1,F2,CF-1) and verify frost-depth steps at perimeter doors. - Slab-on-grade vs. thickened slabs: Track
SFseparately by thickness (4 in,5 in,6 inequipment pads) and price thickened haunches inLFor netCY. - Waste & pump-line prime buffer: Add explicit
5%-8%concrete waste and washout allowance rather than hiding it inside unit labor rates. - Reinforcement & vapor barrier: Count rebar by weight (
TONorLB) including splice laps, corner bars, and15%overlap on welded wire mesh or15-milvapor retarder.
Unit-class sanity check before sealing
Never divide a
SFslab by aCYready-mix quote without carrying thickness explicitly. One dropped0.33 ftdepth conversion turns a 40 CY pour into a 120 CY bust.
- Verify every footing, curb, and equipment pad maps to
CY(material) +LF/SF(formwork) +SF(finish). - Confirm soil export/haul-off from footing excavations is either carried in your Division 31 scope or clearly listed under exclusions.